Project    :     Gold Crest

Client Star Giga Establishment
Consultant WS Atkins
Construction Period 27 months
Completion Date July 2008

Project Brief Supply, Installation, testing and commissioning of the following building services. Electrical: Low Voltage distribution system, Emergency /Fire alarm system.,Lighting protection system.Security system (CCTV, Door access system). Air craft Warning System. Mechanical:-Soil & waste drainage system,Rain water drainage system,Domestic Water system, Mechanical ventilation & Air conditioning system. BMS:-Central control / Building management System